The Representative Office of Regal Petroleum Corporation Limited put into operation the upgraded inhibitor facility at well #61 of Svyrydivske field (Poltava oblast). Within modernization the facility got a new booster compressor station (BSC) and upgraded site for storage of well killing fluid.

The company installed a new BSC, produced by Argentine company GALILEO TECHNOLOGIES. Moreover, it upgraded the site for storing well killing fluid. It enlarged its territory and linked the reservoirs on it with interconnecting piping as well as equipped with pumps, filling pipes and drain system. That made work at the facility much easier and optimized time and resource spendings on the respective operations.

The upgrade of the inhibitor facility was started in March, 2021. From the end of May there were commissioning tests of a new booster compressor station.